Kanban with Scrum
or is it
Scrum with Kanban
© 2018 BeLiminal LLP
@tomjreynolds
uk.linkedin.com/in/tomjreynolds
 Agile Coach & Trainer
 Organisational & Relationship
Systems Coach
 International Conference Speaker
 25+ years in software
development
 Multi Certified Trainer
 Agile since 2007
Tom Reynolds
 Change management
method
 Controls work with WIP limits
 Visualise work
 Flow based
 Pull system
 Process policies are explicit
 Feedback mechanisms
 Collaborative work
 Evolutionary improvement
What is Kanban?
Visualise
Limit WIP
Manage Flow
Make Process
Policies Explicit
Develop Feedback
Mechanisms at
workflow, inter-
workflow &
Organisational
Levels
Improve
Collaboratively
Using “Safe to Fail”
Experiments
 Cadence based
 Empirical
 Time boxed
 Reduces batch
size
 Collaborative
work
 ‘Done’ policies
explicit
 Feedback
mechanisms
 Evolutionary
Improvement
What is Scrum?
Adapted from Mike Cohn – Mountain
Goat Software
Product
Backlog
Refinement
Rule of thumb: 10% of
overall Sprint time
spent on meetings
1 month or
less
The Sprint
Are these methods mutually
exclusive or can they be used
in conjunction with one another
and if so how might that be
possible?
Tasks
(Sprint Backlog -
including at least
1 improvement
item)
Product
Backlog
Selected Product
Backlog
Development Team
Forecast
Product Owner
Discuss and clarify
the selected backlog
Sprint Goal
Product Owner and
Team agree a Sprint
Goal and the Team
forecast the work of
the Sprint
Sprint
Day 1 of The Sprint
8 Hours
Maximum
Scrum Master
Let’s start with Scrum – Sprint Planning
As a
I want
so that...
As a
I want
so that...
As a
I want
so that...
User
Stories To Do
WIP
(Work In Progress)
Done
Task Cards
Task Board
Product Backlog Refinement
Development Team
Product
Backlog Additionally Refined Product
Backlog
Product
Owner
Discuss, refine and
elaborate. Add
acceptance criteria
and size
Initially before
development, then
iteratively every
sprint
No more than 10%
of development
team capacity
Managing refinement
Product Backlog Refinement Sprint Committed User
Stories (Sprint Backlog)
In Progress Ready for
Sprint
Review
WIP Done
The Sprint
Typically 2 weeks – Consider this a 2 week batch of work
Apply WIP limits
Product Backlog
<∞>
Refinement
<16>
Sprint Committed User
Stories (Sprint Backlog)
<Velocity>
In Progress
<3 User Stories>
Ready for
Sprint
Review
<Velocity>
WIP Done
The Sprint
Typically 2 weeks – Consider this a 2 week batch of work – Batch
WIP limited by team velocity
Pull system present with WIP limits
Product Backlog
<∞>
Refinement
<16>
Sprint Committed User
Stories (Sprint Backlog)
<Velocity>
In Progress
<3 User Stories>
Ready for
Sprint
Review
<Velocity>
WIP Done
The Sprint
Typically 2 weeks – Consider this a 2 week batch of work – Batch
WIP limited by team velocity
Pull
Moving downstream
Sprint
Committed
User Stories
(Sprint
Backlog)
<Velocity>
In Progress
<3 User Stories>
Ready for
Sprint
Review
<Velocity>
Sprint
Review
<Velocity>
Ready
to
Deploy
<16>
Analysis and
RFC
<8>
Deploying
<16>
Done
WIP Done
The Sprint
Typically 2 weeks – Consider this a 2 week batch of work – Batch
WIP limited by team velocity
Moving downstream
Sprint
Committed
User Stories
(Sprint
Backlog)
<Velocity>
In Progress
<3 User Stories>
Ready for
Sprint
Review
<Velocity>
Sprint
Review
<Velocity>
Ready
to
Deploy
<16>
Analysis and
RFC
<8>
Deploying
<16>
Done
WIP Done
The Sprint
Typically 2 weeks – Consider this a 2 week batch of work – Batch
WIP limited by team velocity
Pull
Commitment and Measurement
Options Refinement Sprint
Committed
In
Progress
Ready
for
Sprint
Review
Sprint
Review
Ready to
Deploy
Analysis
and RFC
Deploying Done
Customer Lead Time
Commitment is
Deferred
Abandon prior to
commitment
Commitment
Point
Can consider this
to be discovery
Kanban system or Scrum system?
Options
<∞>
Refinement
<16>
Sprint
Committed
User Stories
(Sprint
Backlog)
<Velocity>
In
Progress
<3 User
Stories>
Ready for
Sprint
Review
<Velocity>
Sprint
Review
<Velocity>
Ready to
Deploy
<16>
Analysis
and RFC
<8>
Deploying
<16>
Done
WIP Done WI
P
Done
Moving further upstream
Project
ideas
<∞>
Initiate
<1-2>
Story
Mapping
<1>
Options
<1
project>
Refinement
<16>
Sprint
Committed
User
Stories
(Sprint
Backlog)
<Velocity>
In
Progress
<3 User
Stories>
Ready
for
Sprint
Review
<Velocity>
Sprint
Review
<Velocity>
Ready
to
Deploy
<16>
Analysis
and RFC
<8>
Deploying
<16>
Done
WIP
Done
WIP Done WIP Done WIP Done
Discovery
Delivery
Scaling across teams
Project
ideas
<∞>
Initiate
<1-2>
Story
Mapping
<1>
Options
<1
project
>
Refinement
<16 per
team>
Sprint
Committed
User Stories
(Sprint
Backlog)
<Velocity
per team>
In
Progress
<3 User
Stories
per team>
Ready
for
Sprint
Review
<Velocity
per team>
Sprint
Review
<Velocity
per team>
Ready
to
Deploy
<16>
Analysi
s and
RFC
<8>
Deploying
<16>
Done
WIP
Done
WIP
Done
TeamA
WIP Done
WIP
Done
TeamB
Managing across a value stream?
© 2013 The Agile Mindset Ltd
Concept
Cash
The question was
“Kanban with Scrum
or is it
Scrum with Kanban”
What do you think?
© 2018 BeLiminal LLP

More Related Content

Kanban with scrum or is it scrum with kanban.001

  • 1. Kanban with Scrum or is it Scrum with Kanban © 2018 BeLiminal LLP
  • 2. @tomjreynolds uk.linkedin.com/in/tomjreynolds  Agile Coach & Trainer  Organisational & Relationship Systems Coach  International Conference Speaker  25+ years in software development  Multi Certified Trainer  Agile since 2007 Tom Reynolds
  • 3.  Change management method  Controls work with WIP limits  Visualise work  Flow based  Pull system  Process policies are explicit  Feedback mechanisms  Collaborative work  Evolutionary improvement What is Kanban? Visualise Limit WIP Manage Flow Make Process Policies Explicit Develop Feedback Mechanisms at workflow, inter- workflow & Organisational Levels Improve Collaboratively Using “Safe to Fail” Experiments
  • 4.  Cadence based  Empirical  Time boxed  Reduces batch size  Collaborative work  ‘Done’ policies explicit  Feedback mechanisms  Evolutionary Improvement What is Scrum? Adapted from Mike Cohn – Mountain Goat Software Product Backlog Refinement Rule of thumb: 10% of overall Sprint time spent on meetings 1 month or less The Sprint
  • 5. Are these methods mutually exclusive or can they be used in conjunction with one another and if so how might that be possible?
  • 6. Tasks (Sprint Backlog - including at least 1 improvement item) Product Backlog Selected Product Backlog Development Team Forecast Product Owner Discuss and clarify the selected backlog Sprint Goal Product Owner and Team agree a Sprint Goal and the Team forecast the work of the Sprint Sprint Day 1 of The Sprint 8 Hours Maximum Scrum Master Let’s start with Scrum – Sprint Planning
  • 7. As a I want so that... As a I want so that... As a I want so that... User Stories To Do WIP (Work In Progress) Done Task Cards Task Board
  • 8. Product Backlog Refinement Development Team Product Backlog Additionally Refined Product Backlog Product Owner Discuss, refine and elaborate. Add acceptance criteria and size Initially before development, then iteratively every sprint No more than 10% of development team capacity
  • 9. Managing refinement Product Backlog Refinement Sprint Committed User Stories (Sprint Backlog) In Progress Ready for Sprint Review WIP Done The Sprint Typically 2 weeks – Consider this a 2 week batch of work
  • 10. Apply WIP limits Product Backlog <∞> Refinement <16> Sprint Committed User Stories (Sprint Backlog) <Velocity> In Progress <3 User Stories> Ready for Sprint Review <Velocity> WIP Done The Sprint Typically 2 weeks – Consider this a 2 week batch of work – Batch WIP limited by team velocity
  • 11. Pull system present with WIP limits Product Backlog <∞> Refinement <16> Sprint Committed User Stories (Sprint Backlog) <Velocity> In Progress <3 User Stories> Ready for Sprint Review <Velocity> WIP Done The Sprint Typically 2 weeks – Consider this a 2 week batch of work – Batch WIP limited by team velocity Pull
  • 12. Moving downstream Sprint Committed User Stories (Sprint Backlog) <Velocity> In Progress <3 User Stories> Ready for Sprint Review <Velocity> Sprint Review <Velocity> Ready to Deploy <16> Analysis and RFC <8> Deploying <16> Done WIP Done The Sprint Typically 2 weeks – Consider this a 2 week batch of work – Batch WIP limited by team velocity
  • 13. Moving downstream Sprint Committed User Stories (Sprint Backlog) <Velocity> In Progress <3 User Stories> Ready for Sprint Review <Velocity> Sprint Review <Velocity> Ready to Deploy <16> Analysis and RFC <8> Deploying <16> Done WIP Done The Sprint Typically 2 weeks – Consider this a 2 week batch of work – Batch WIP limited by team velocity Pull
  • 14. Commitment and Measurement Options Refinement Sprint Committed In Progress Ready for Sprint Review Sprint Review Ready to Deploy Analysis and RFC Deploying Done Customer Lead Time Commitment is Deferred Abandon prior to commitment Commitment Point Can consider this to be discovery
  • 15. Kanban system or Scrum system? Options <∞> Refinement <16> Sprint Committed User Stories (Sprint Backlog) <Velocity> In Progress <3 User Stories> Ready for Sprint Review <Velocity> Sprint Review <Velocity> Ready to Deploy <16> Analysis and RFC <8> Deploying <16> Done WIP Done WI P Done
  • 16. Moving further upstream Project ideas <∞> Initiate <1-2> Story Mapping <1> Options <1 project> Refinement <16> Sprint Committed User Stories (Sprint Backlog) <Velocity> In Progress <3 User Stories> Ready for Sprint Review <Velocity> Sprint Review <Velocity> Ready to Deploy <16> Analysis and RFC <8> Deploying <16> Done WIP Done WIP Done WIP Done WIP Done Discovery Delivery
  • 17. Scaling across teams Project ideas <∞> Initiate <1-2> Story Mapping <1> Options <1 project > Refinement <16 per team> Sprint Committed User Stories (Sprint Backlog) <Velocity per team> In Progress <3 User Stories per team> Ready for Sprint Review <Velocity per team> Sprint Review <Velocity per team> Ready to Deploy <16> Analysi s and RFC <8> Deploying <16> Done WIP Done WIP Done TeamA WIP Done WIP Done TeamB
  • 18. Managing across a value stream? © 2013 The Agile Mindset Ltd Concept Cash
  • 19. The question was “Kanban with Scrum or is it Scrum with Kanban” What do you think? © 2018 BeLiminal LLP

Editor's Notes

  1. Stand and form pairs and triads In your groups share with your colleagues two things What you want to learn today? What you already know about this topic
  2. TR
  3. EH
  4. After Planning Meeting I – COMMITMENT – as a contract between Team and Product Owner. Explain the differences between Tactical level and Strategy Level
  5. Example Task Board
  6. After Planning Meeting I – COMMITMENT – as a contract between Team and Product Owner. Explain the differences between Tactical level and Strategy Level
  7. Is this a Kanban system, Scrum system or something else Stand to the left if it is a Kanban system Stand to the right if it is a Scrum system Stand in the middle if it is something else Discuss in pairs and triads why you think it is what you have chosen
  8. Is this a Kanban system, Scrum system or something else Stand to the left if it is a Kanban system Stand to the right if it is a Scrum system Stand in the middle if it is something else Discuss in pairs and triads why you think it is what you have chosen
  9. Table talk Stand and forms pairs and triads In your group share with each other the most important concept that you learned from the training Answer and discuss the question “Is it Kanban with Scrum or is it Scrum with Kanban”