SlideShare a Scribd company logo
Earned Value Management Systems (EVMS) 
32 Guidelines Summary in ANSI/EIA 748 Intent Guide 
REF: ANSI/EIA 748 Intent Guide 
Summarized By  
Muhammad El-Chammakh
Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs
1
Define Work Scope 
(WBS)
The Work Breakdown Structure (WBS) is used as the basic building block for 
the planning of all authorized work. The WBS is a product‐oriented division 
of project tasks depicting the breakdown of work scope for work 
authorization, tracking, and reporting purposes that facilitates traceability 
and provides a control framework for integrated program management. It 
should ensure that the Statement of Work (SOW) is entirely covered and 
allow for the integration of technical, schedule, and cost information. The 
WBS also facilitates communications as it establishes a common frame of 
reference for customers, management, and Integrated Product Teams 
(IPTs). 
A WBS is a direct representation of the work scope in the project, documenting the hierarchy and 
description of the tasks to be performed and their relationship to the product deliverables. The 
WBS breaks down all authorized work scope into appropriate elements for planning, budgeting, 
scheduling, cost accounting, work authorization, measuring progress, and management control.  
The WBS must be extended to the level necessary for management action and control based on 
the complexity of the work.  At a minimum, the WBS is extended to the level or levels at which 
control accounts are established.  A WBS dictionary is typically used to define the work scope for 
each unique element in the WBS. 
1) Only one WBS is used per project and it contains all project 
work, including revisions for authorized changes and 
modifications.
2) The WBS contains all contract line items and end items.
3) The WBS identifies all WBS elements specified for external 
reporting.
4) The WBS is extended at a minimum to the level(s) at which 
control accounts are established.
5) The WBS elements should collectively provide a complete 
definition of work scope requirements.
6) The WBS may evolve as the project requirements change.
2
Define Project 
Organization (OBS)
The OBS helps management focus on establishing the most efficient 
organization by taking into consideration the availability and capability of 
management and technical staff, including subcontractors, to achieve the 
project objectives.  
Assign organizational responsibility for the project work. An OBS is used to facilitate the 
assignment of responsibility, accountability, and authority for all tasks to be performed. An OBS is 
a direct representation of the hierarchy and provides a description of the organizations 
established to provide resources as well as to plan and perform the work tasks. The OBS identifies 
the organization responsible for each segment of work, including subcontracted and intra‐
organizational effort. The assignment of lower‐level work segments to responsible managers 
should provide key control points for management purposes. When effort is subcontracted, the 
applicable subcontractor is identified and related to the appropriate WBS element(s) and/or 
organization charged with acquiring the subcontracted item. 
1) All authorized work is assigned to organizational 
elements.
2) Organization elements are work teams, functions, or 
whatever organization units are used by the company for 
execution of the program work efforts.
3) Major subcontractor work efforts are integrated into 
the program structure. 
3 Integrate Processes
The integration of planning, scheduling, budgeting, work authorization, and 
cost accumulation management processes provides the capability for 
establishing the Performance Measurement Baseline (PMB), identifying 
work progress, and collecting actual costs, facilitating management analysis 
and corrective actions. The WBS and OBS allow summarization of cost data 
from the detail level through both the WBS and the OBS to the appropriate 
project level needed for management insight and control.  
Integrate the technical, schedule, and cost elements of the project through project plans that 
include schedules, budgets, authorization of work, and accumulation of costs, all consistent with 
the budget plan. The work tasks are assigned to a WBS and OBS and are traceable to the planning 
and budgeting system and the cost collection system. Establishment of a unique coding structure 
facilitates the linkage between the planning, scheduling, budgeting, work authorization, cost 
accumulation, and performance measurement processes.  
1) Master, intermediate, and detail level schedules.
2) Manufacturing Requirements Planning (MRP) or 
Enterprise Requirements Planning (ERP) operational 
schedules.
3) Control account plans.
4) Management performance reports by WBS and OBS.
5) Responsibility Assignment Matrix (RAM).
6) Statement of Work.
7) Work authorizations.
4
Identify Overhead 
Management
Visibility into direct and indirect costs is essential for successful 
management of a project. Therefore, it is important to have a documented 
process and organizations established specifically to manage and control 
indirect costs.  
Indirect costs are for common activities that cannot be identified specifically with a particular 
project or activity and should typically be budgeted and controlled separately at the functional or 
organizational manager level. Clearly identify managers who are assigned responsibility and 
authority for controlling indirect costs, and who have the authority to approve expenditure of 
resources. The process for management and control of indirect costs, including assignment of 
responsibility, is typically documented in the organization’s approved accounting procedures. 
1) Cost Accounting Standards (CAS) disclosure statement.
2) Organizational chart.
3) Chart of accounts.
Earned Value Management Systems
REF :ANSI/EIA‐748 Intent Guide 
The 32 Guidelines Summary 
1 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs
Earned Value Management Systems
REF :ANSI/EIA‐748 Intent Guide 
The 32 Guidelines Summary 
5
Integrate WBS/OBS to 
Create Control 
Accounts
The careful establishment of the control account structure ensures the 
proper level of management is established based on the complexity of the 
work and the capability of the organization.  It also establishes the lowest 
level of performance measurement necessary for program management. 
The integration of the WBS and OBS creates control accounts that facilitate schedule and cost 
performance measurement.
The control account is the point where the WBS tasks and OBS responsibility intersect. It is 
defined as the point where a single functional organization or integrated product team has 
responsibility for work defined to a single WBS element. There may be multiple control accounts 
within a responsible OBS element when the effort within a WBS element must be segregated for 
management control purposes driven by scope and exit criteria (i.e., completion of task scope). 
The establishment of multiple control accounts should be determined by the control account’s 
scope of the management tasks and consideration for planning and control of budgets, schedules, 
work assignments, progress assessment, problem identification, and corrective actions.     
1) Control accounts.
2) Responsibility Assignment Matrix (RAM).
3) Management performance reports.
6
Schedule with 
Network Logic
Scheduling authorized work facilitates effective planning, statusing, and 
forecasting, all of which are critical to the success of all projects. The 
integration of the technical, schedule, and cost aspects of the project 
results in the:
1) Expected sequence of work.
2) Establishment of significant interdependencies between work packages 
and planning packages (or lower‐level tasks/activities) that determine total 
work time and critical path through the project.               
3) Time‐phasing of authorized discrete work for use as a performance 
measurement baseline.
The scheduling process documents and the resulting project schedule provide a logical sequence 
of work leading to a milestone, event, or decision point needed to ensure that the schedule 
supports the project objectives. The master schedule aligns to the contractual period of 
performance except when an Over‐Target Schedule (OTS) has been approved for implementation.  
There is a clear definition of what constitutes commencement and completion of each work 
package and planning package (or lower‐level task/activity). While no specific scheduling software 
is required, there must be horizontal and vertical integration of the schedule through the 
framework of the WBS and OBS.
Government development programs or significant development efforts typically schedule the 
discrete authorized work through the use of a network schedule. Production programs typically 
schedule using a Manufacturing Requirements Planning (MRP) or Enterprise Requirements 
Planning (ERP) tool employing a line of balance schedule that supports the project objectives.           
1) Integrated network schedules including master, 
intermediate (if any), and detailed schedules.                 
2) MRP or ERP schedules, or planned order reports.
3) Control account plans (may be separate plans or detail 
schedules).
4) Work authorization documents.
7
 Set Measurement 
Indicators
Objective indicators enable measurement of work accomplished, thereby 
allowing its accurate comparison to planned work. Meaningful performance 
metrics enable better management insight and decision‐making, ensuring 
that maximum time is allowed for management action to keep the project 
on plan. 
1) The purpose for identifying objective indicators is to provide a means to measure the quantity 
of work accomplished – the earned value.  There is a direct relationship between the budget at 
completion and earned value.  The time‐phased budget assigned to the work scope is the basis for 
computing the earned value for work accomplished.  Performance measures are one aspect of an 
integrated program management system as other processes control the quality and technical 
content of the work performed.
2)Identify objective interim performance measures within control accounts (or lower‐level 
tasks/activities) to enable accurate performance assessment each month. The master schedule 
includes key program and contractual requirements. It enables the team to predict when 
milestones, events, and program decision points can be expected to occur. Lower‐tier schedules, 
when utilized, must contain specific control account (or lower‐level task/activity) start and finish 
dates that are based on physical accomplishment and are clearly consistent with program time 
constraints.
1) Integrated schedules including master, intermediate (if 
any), and detailed schedules that identify contract 
milestones and key events.
2) MRP or ERP production planned order reports.
3) Control account plans (may be separate plans or detail 
schedules).
8
Establish Budgets for 
Authorized Work
The time‐phased performance measurement baseline that represents the 
planned scope of all authorized work and schedule provides the program 
manager a reference to assess project performance. It is controlled and 
reconciled to the target cost plus authorized unpriced work less 
management reserve. It represents the cumulative, time‐phased, budgeted 
cost for work scheduled. The performance measurement baseline is a key 
component of earned value management. 
1) The Contract Budget Base (CBB) represents the value of all authorized work.  This includes the 
negotiated contract cost (NCC) plus the estimated cost of any authorized unpriced work (AUW). 
This CBB value forms the basis for program budgeting.          
2) The assignment of budgets to scheduled segments of work produces a plan against which actual 
performance can be compared. This is called the Performance Measurement Baseline (PMB). The 
establishment, maintenance, and use of the PMB are indispensable to effective performance 
measurement. The PMB should be in place as early as possible after project award or 
Authorization to Proceed (ATP).
3) The PMB represents the time‐phased scope, schedule, and associated budget through the end 
of the contract. It is the sum of the control accounts plus any summary level planning packages 
(SLPP) and undistributed budget.  Undistributed budget is a transient account that is distributed to 
control accounts, summary level planning packages, or management reserve as soon as practical 
after definitization, or as contractually directed.   
1) Control account plans.
2) Summary level planning packages.
3) Performance measurement baseline.
4) Undistributed budget logs.
5) Notification to the customer of an over‐target baseline 
or over‐target schedule.
6) Work authorization document.
2 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs
Earned Value Management Systems
REF :ANSI/EIA‐748 Intent Guide 
The 32 Guidelines Summary 
9
Budget by Cost 
Elements
An essential part of project planning and establishing a performance 
measurement baseline is the establishment of budgets for all the 
authorized work. Identification of the budget cost elements documents the 
required resources and places work scope with the performing 
organization. 
Through a work authorization process, establish budgets for all authorized work to be done by the 
responsible organizational elements. No work should begin before the effort is authorized by an 
initial work authorization. As budgets and schedules are established and approved for all the 
authorized work at the control account level, the work authorization is updated as required. The 
work authorization at the control account level is where the approved work scope, period of 
performance, and budget are integrated. The control accounts identify the appropriate cost 
elements (labor, subcontract, material, and other direct costs). It is important to include all 
resources required to accomplish the work scope. 
1) Control account plans by element of cost.
2) Work authorization documents.
3) Performance measurement baseline.
4) Undistributed budget logs.
5) Bills of Materials (BOM).
6) Responsibility assignment matrix .
7) Schedules, if resourced.
10
Create Work 
Packages, Planning 
Packages
Budgets, established at the work package level identifying specific resource 
requirements in dollars, hours, or other measurable units, provide the 
detail for effective execution of the baseline plan. The resources are to be 
time‐phased the way the detail work is to be accomplished. This approach 
provides meaningful product‐related or management‐oriented events for 
performance measurement. Where a control account cannot be planned in 
work package detail, the work scope, budget, and schedule requirements 
are held in planning packages. The master schedule may have more detail 
below the work package/planning package level to support the 
development of a realistic critical path, as applicable. 
Effort contained within a control account is distributed into either work packages or planning 
packages. Work packages are single tasks assigned to a performing organization for completion 
and are natural subdivisions of control account effort, resulting in a definable end product or 
event. Work package descriptions must clearly distinguish one work package effort from another. 
When work packages are relatively short, little or no assessment of work‐in‐progress is required. 
As work package length increases, work‐in‐progress measurement becomes more subjective, 
unless objective techniques, such as discrete milestones with pre‐assigned budget values or 
completion percentages, subdivide them. A key feature, from the standpoint of evaluating 
accomplishment, is the desirability of having work packages that incorporate frequent, objective 
indicators of progress. 
1) Control account plans divided into work packages and 
planning packages.
2) Control account schedules.
3) Control account time‐phased budgets. 
11
Sum Detail Budgets to 
Control Account
The integrity of the performance measurement baseline requires that the 
budget of the control account equal the sum of its work package and 
planning package budgets. When the budget of the control account equals 
the sum of its work package and planning package budgets, it prevents 
duplicate recording of budgets. 
All control accounts must contain a budget, schedule, and scope of work and should realistically 
represent the work assigned and budgeted to the organizational units. In all cases, the value of 
the budget assigned to individual work packages and planning packages within the control 
account must sum to the total value authorized for the control account. A control account 
manager should not have a budget without an assigned scope of work. Conversely a control 
account manager should not have authorized scope without associated budget.
1) Control account plan total budget.
2) Work package budget.
3) Planning package budget.
12
LOE Planning and 
Control
Meaningful product‐ or management‐oriented events are critical for 
performance measurement. Objective measurement of Level of Effort (LOE) 
activity is impracticable and provides little, if any, visibility into actual 
performance; therefore, its use must be minimized. 
Each task on the project needs to be assessed to determine the best method to budget and 
measure its progress toward completion. Level of effort is defined as having no measurable 
output or product that can be discretely planned at the work package level. Level of effort must 
be limited to those activities that are unable to be measured discretely to avoid distorting project 
performance data. Level of effort work packages should be separately identified from discrete 
effort work packages and apportioned effort work packages. Budgets for level of effort activity 
must have a sound basis of estimate and be time‐phased to properly reflect when work will be 
accomplished. LOE budgets may be planned at either the control account level or at the same 
level as discrete or apportioned work packages.  
1) Control account plans identify level of effort work 
packages and budgets.
13
Establish Overhead 
Budgets
The overall value of establishing indirect budgets lies in the ability of 
company management to manage cost elements that cannot be directly 
assigned to individual cost objects (products).  By comparing actual indirect 
expenses to established indirect budgets, the company can determine if the 
absorption of indirect expenses based on existing documented allocation 
schemes is on track or if allocation rates will need to be adjusted.  The 
accurate assignment of indirect expenses, therefore, ensures that each 
program will only receive its fair share of indirect costs. 
Establish indirect budgets at the appropriate organizational level for each pool and cost sub‐
element. It is important to have an indirect budgeting and forecasting process, because indirect 
costs can account for a major portion of the cost of any project. As such, the budgetary control 
and management of this category of cost cannot be overlooked or minimized. Indirect budgets on 
the project are established and planned with the established direct budgets consistent with the 
method by which allocation of indirect costs will ultimately be made to the project. This 
methodology is normally described in the organization’s accounting procedures. 
1) Documented process for managing indirect costs.
2) Organizational structure identifying ownership 
responsibility and authority levels.
3) Indirect cost policies and procedures.
4) Chart of accounts.
14
Identify Management 
Reserve and 
Undistributed Budget
To ensure that budget for newly authorized efforts remains tied to the 
associated scope during the initial planning process, Undistributed Budget 
(UB) has been designated as the short‐term holding account. Once the 
responsible organization(s) has been identified, the budget will transfer 
from undistributed budget to the appropriate control account(s). This 
ensures budget and scope will not be transferred independently. 
1) Identify and control management reserve and undistributed budget. Management reserve is 
budget set aside for unplanned events that may arise during the course of the project. Because 
management reserve is budget that is not yet tied to work, it does not form part of the 
performance measurement baseline. The management reserve budget should be commensurate 
with the level of risks and opportunities identified by the project or withheld for management 
control purposes.
2) Undistributed budget is budget that is applicable to specific project effort, but has not yet been 
distributed below the project level either directly to control accounts or to summary level 
planning packages. It is a transient amount because, once it is distributed to either control 
accounts or to summary level planning packages, it ceases to be undistributed budget. Because 
undistributed budget is budget that is tied to work, it does form part of the performance 
measurement baseline. Undistributed budget accounts are to be cleared in a reasonably timely 
manner as work scope is finalized and distributed to control accounts or to summary level 
1) Project control logs (management reserve, 
undistributed budget, performance measurement 
baseline, and contract budget base).
2) Management performance reports.
3 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs
Earned Value Management Systems
REF :ANSI/EIA‐748 Intent Guide 
The 32 Guidelines Summary 
15
Reconcile to Target 
Cost Goal
A project baseline that reflects the common agreement between the two 
parties provides a common reference point for progress assessment. It 
provides recognition of contractual requirements and precludes 
unauthorized changes to the performance measurement baseline. The 
project target cost must be reconciled with the performance measurement 
baseline and management reserve.  
Reconcile the project value (target cost plus authorized, unpriced work) with the sum of all control 
account budgets, indirect budgets, management reserves, and undistributed budgets. 
1) Project control logs (management reserve, 
undistributed budget, performance measurement 
baseline, and contract budget base) reconciled to project 
target cost.
2) Management performance reports.
3) Internal report showing the summarization from cost 
account to the performance measurement baseline.
16 Record Direct Costs
Direct cost must be assigned to a project consistent with the pertinent 
budgets in order to achieve effective performance management. A project’s 
cost‐charging structure established in the accounting system should help 
ensure that actual costs collected are directly compared with associated 
budgets for that work.  
1) Accumulate direct costs in the formal accounting system in a manner consistent with the way 
the related work is planned and budgeted. Actual costs reported in the performance reports agree 
with the costs recorded in the general books of account (accounting system) or can be explained 
as timing differences.  At a minimum, actual costs are collected at the control account level to 
enable summarization of cost by both the WBS and OBS.  Timing differences that may occur 
between the accounting system and project performance reports must be reconcilable.
2) Subcontracts also require special consideration. Subcontract costs must be accrued in a timely 
manner consistent with the schedule status. This may require the use of estimated costs or the 
equivalent import from the subcontractor’s books of record or report.  
1) Reconciliation of project costs with the accounting 
system.
2) Actual costs are reported at the control account level 
at a minimum.
3) Reconciliation of subcontract reported actual costs to 
subcontract payments.
4) Internal and external performance reports for 
subcontractors.
17
Summarize Direct 
Costs by WBS 
Elements
Actual costs need to be available at all levels of the WBS to support project 
management with performance measurement data. Cost collection 
accounts mapped to the WBS. The WBS roll‐up structure contains no 
division/allocation of lower‐level cost to multiple higher‐level WBS 
elements, which helps to ensure performance measurement data integrity 
when summarized by WBS.  
A work order/job order/task code charge number structure must exist that uniquely identifies 
costs at the control account level allowing for accumulation and summarization of costs to higher 
levels of the work breakdown structure. Through the use of this coding structure, allowable costs 
collected within the control account by element of expense roll‐up from the control account level 
through the WBS to the top level without being divided among two or more higher‐level WBS 
elements. Cost collection accounts map to the WBS, and the WBS roll‐up structure contains no 
division/allocation of lower‐level cost to multiple higher‐level WBS elements. When common 
costs are collected in separate control accounts for like items or services they are allocated to 
appropriate control accounts in each project.  
1) Cost collection account structure.
2) WBS/cost collection mapping.
3) Management performance reports.
18
Summarize Direct 
Costs by OBS Elements
Actual costs need to be available at all levels of the OBS to support project 
management with performance measurement data. Cost collection 
accounts mapped to the OBS, and the OBS roll‐up structure containing no 
division/allocation of lower‐level cost to multiple higher‐level OBS 
elements, helps to ensure performance measurement data integrity when 
it is summarized by OBS.  
Allowable costs collected within the control account by element of expense “roll‐up”, from the 
control account level through the OBS, to the top level without being divided at any level among 
two or more higher‐level elements. This guideline and the one before it are identical, with the 
exception that this one deals with OBS data summarization while the previous one dealt with WBS 
data summarization. In either case the intent is the same: actual cost collected at the control 
account level may not be rolled up (i.e., summarized) to multiple higher‐level elements. When 
common costs are collected in separate control accounts for like items or services, they are 
allocated to appropriate control accounts in each project.  
1) Responsibility assignment matrix.
2) Organization charts.
3) OBS structure (roll‐up scheme).
4) Management performance reports.
19
Record/Allocate 
Indirect Costs
Visibility into direct and indirect costs is essential for successful 
management of a project. Therefore, it is important to have a documented 
process and organizations established specifically to manage and control 
indirect costs. 
Indirect costs are for common activities that cannot be identified specifically with a particular 
project or activity and should typically be budgeted and controlled separately at the functional or 
organization managerial level. Record all indirect costs for the project in the accounting system. 
Allocate them to the recorded direct costs per the documented procedure to ensure that all 
projects benefiting from the indirect costs will receive their fair share. 
1) Cost collection account structure.
2) WBS/cost collection mapping.
3) Cost accounting standards disclosure statement.
20
Identify Unit and Lot 
Costs
A manufacturing accounting system capable of isolating unit and lot costs in 
a production environment should allow the flexibility to plan, measure 
performance, and forecast in a more efficient way when there are multiple 
projects in the same production line.  
When using equivalent units, or lot costs budgeting, ensure that the accounting system produces 
actual unit, equivalent unit, or lot costs for purposes of measuring cost performance.  Typically 
this is accomplished through the use of a charge number structure, the manufacturing planning 
systems, or equivalent capability. On production contracts or projects where multiple similar units 
are being delivered, or when units are taken off the line in more or less a random order according 
to the delivery agreements of the different customer’s projects, it is sufficient to establish 
“equivalent unit cost” (i.e., all things being equal, each unit’s cost is approximately equivalent to 
every other unit’s cost). 
1) Project cost collection structure (MRP).
2) ERP system supports the identification of unit costs, 
equivalent unit costs, or lot costs when needed, including 
differentiation of work in process.
4 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs
Earned Value Management Systems
REF :ANSI/EIA‐748 Intent Guide 
The 32 Guidelines Summary 
21
Track and Report 
Material Costs and 
Quantities
1) The establishment of a valid comparison of planned material costs for 
completed work with the actual material costs for that work provides the 
basis for realistic evaluation of cost deviations and ultimately facilitates 
cost at complete projections.  Residual inventory provides visibility into 
excess material for the current deliverables available for replacement of 
failures in the current project or future projects having similar deliverables.  
2) Long lead critical material items may require special considerations for 
planning and measuring progress.  Contracting methods should be 
considered that support objectives and promote the use of progress 
methods to meet the needs of integrated program management. 
Material costs must be accurately charged to contract control accounts using recognized, 
acceptable costing techniques. The need for accurate comparison of material costs to material 
budgets and earned value requires that the appropriate point of performance measurement for 
material is established. The generally acceptable points for measuring material progress are:            
1) Point of receipt (acceptance).
2) Point of stock (inventory).
3) Point of issue to work in process (consumption).
1) Management performance reports.
2) Control account plans.
3) Material system reports.
22
Calculate Schedule 
Variance and Cost 
Variance
Earned Value Management System (EVMS) performance data reconciles to 
the general books of account (accounting system) and provides for 
management control. Visibility into project performance helps the project 
manager to focus resources on those areas in need of attention.
On at least a monthly basis, generate schedule variance and cost variance data that supports 
management control needs by allowing the project manager to focus on those areas in need of 
attention. The intent of this guideline is to recognize that analysis must be accomplished on a 
regular, periodic basis. It is critical that the calculation of earned value (see guidelines 7 and 10) be 
based consistently with the manner used to establish the budgets (see guidelines 8, 10, and 12). 
This ensures a generation of valid variances for analysis purposes.  All data analyzed must come 
from, or be reconcilable with, the earned value management system (BCWS, BCWP, and ACWP) 
and the accounting system. 
1) Monthly performance reports (cost variance, schedule 
variance, and variance at completion analysis).                
2) Variance analysis data (root causes, impacts at 
completion, and management actions).
23
Identify Significant 
Variances for Analysis
The ability to analyze deviations from the established plan permits 
management at all levels to rapidly and effectively implement corrective 
actions in an effort to regain project/contract objectives.  Without this 
visibility into and the understanding of plan deviations, the success of the 
project can be jeopardized.  Additionally, insight into future cost and 
schedule performance, based on the analysis of variances, will be 
facilitated.  
1) The purpose of this guideline is to ensure both significant schedule and cost variances are 
analyzed, at least monthly, at a level of detail required to manage the effort; i.e., to enable 
management decision‐making and corrective action.              
2) Comparing the budget value of work completed to the budget value of work scheduled during a 
given period of time provides a valuable indication of schedule status in terms of dollars‐worth of 
work accomplished. This schedule variance (SV) may not clearly indicate whether or not scheduled 
milestones are being met, since some work may have been performed out of sequence or ahead 
of schedule while other work has been delayed. Schedule variance does not indicate whether a 
completed activity is a critical event or if (or by how much) delays in an activity’s completion will 
affect the completion date of the project.  
1) Variance analyses (budget based schedule variances 
and cost variances).
2) Management action plans.
3) Updated schedule task completion and cost‐at‐
completion forecasts.
24
Analyze Indirect Cost 
Variances
Ongoing indirect cost analysis provides visibility into potential indirect cost 
overruns and the opportunity to develop and implement management 
action plans to meet project objectives.
Indirect rate forecast and control are crucial to meeting project cost objectives. This guideline 
requires a monthly indirect cost analysis, by those assigned responsibility, comparing indirect 
budgets to indirect actual costs and explaining the cause of resultant variance(s). The importance 
of analyzing indirect cost performance requires the exercise of maximum discipline in following 
the established indirect cost control procedures. The results of indirect analysis are provided to 
program and business managers for their use in forecasting the impact to the program Estimate at 
Completion (EAC). 
1) Indirect cost variance analyses.
2) Indirect cost management action plans.
3) Indirect cost updated schedule and cost forecasts.
25
Summarize 
Information for 
Management
Understanding the relationship among scope, cost, schedule, and risk is 
critical to successful project execution. Variances provide an understanding 
of project conditions, allowing the project manager to properly address 
project issues, risks, and opportunities. They also identify significant 
problem areas coming from all levels of the organization and project scope 
of work, derived from the same data sources. Variances provide valuable 
management information. 
Use the same data for internal management needs and for reporting to the customer. Since the WBS and 
the OBS exist as a formal and disciplined framework for project management and also provide a formal 
structure for the comprehensive roll‐up of all data elements, they become the ideal framework for 
summarizing data from the control account level to the management reporting level. Summarizing 
performance information assists senior levels of management to focus on the significant problems that 
require their intervention.  
1) Variance analyses.
2) Schedule and cost performance reports.
3) Management action plans.
4) Updated schedule and cost forecasts.
26
Implement Corrective 
Actions
Earned value management information provides management with early 
insight into the extent of problems. Management action is required to 
mitigate the impacts on the project objectives.
1) Identify and implement corrective actions based on earned value variance analysis to achieve project 
objectives. Regular monitoring of the performance data helps keep the program within its cost and 
schedule baseline objectives.
2) Performance measurement data should be utilized by all levels of management to promote effective 
project execution. Because of this, the data produced by the earned value management system must be 
available to managers on a timely basis and must be of sufficient quality to ensure that effective integrated 
program management decisions can be made as a result of its analysis. The project’s internal reports and 
the reports forwarded to their customer must indicate the overall cost and schedule impacts of such 
problems on the project.  
1) To‐Complete Performance Index (TCPI).
2) Independent completion estimates.
3) Risk and opportunity management data and similar 
metrics.
4) Management action plans and review briefings.
5 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs
Earned Value Management Systems
REF :ANSI/EIA‐748 Intent Guide 
The 32 Guidelines Summary 
27
Revise Estimate at 
Completion (EAC)
A properly established and maintained estimate at completion (EAC) will 
ensure continuing visibility into the cost, schedule, risks and opportunities, 
as well as the resource needs (e.g., labor, material, etc.) for the remaining 
work that is essential to project success for both the customer and the 
contractor.  Accurate estimates support the customer’s ability to provide 
sufficient funding to the project and enhance internal management’s 
visibility into critical issues and resource requirements.  
1) The control account level is where the approved work scope, period of performance, budget, and 
estimate at completion (EAC) are integrated.  The estimates at completion are summarized up through the 
WBS and OBS to the program level for management visibility and control.  The control account managers 
are responsible for maintaining the control account level latest revised estimate to complete that is 
assessed on a monthly basis. Periodically, a comprehensive or bottom‐up estimate at completion should be 
prepared using all available information to arrive at the best possible estimate at completion.
2) For the monthly estimates to complete (ETC), the control account manager should review the status of 
the expended effort and the achievability of the forecast and significant changes briefed to program 
management. This analysis should focus on performance to date within the control account, an assessment 
of the effort to complete the remaining work, and an evaluation of the type and quantity of resources 
required to complete the effort. Issues, risks and opportunities should also be considered in this analysis. 
When updates are made to existing forecasts of the schedule and cost to complete, significant changes are 
briefed to program management. Prudent maintenance of the control account‐level estimates at 
completion ensures that the EAC reflects a valid projection of project costs.  
1) Control account plans.
2) Documented process for developing EACs, including 
subcontractor EAC integration.
3) Basis of estimates.
4) Risk and opportunity management plans 
(identification, analysis, and handling plans).                
5) Updated schedule task completion and cost‐at‐
completion forecasts.
28
Incorporate Changes 
in a Timely Manner
A properly maintained performance measurement baseline is crucial to 
effective program management.  The timely and accurate incorporation of 
contractual changes ensures that the information generated from the 
execution of the baseline plan provides an accurate picture of progress and 
facilitates correct management actions and decisions.  
1) Incorporate the work scope for authorized changes into the performance measurement baseline in a 
documented, disciplined, and timely manner. The timely and accurate incorporation of authorized and 
negotiated changes into the performance measurement baseline ensures that valid performance 
measurement information is generated for the new scope being executed. Adherence to this guideline 
helps to ensure that budget, schedule, and work remain coupled.                 
2) For unpriced change orders, the contractor will develop its best estimate for planning and budgeting 
purposes for incorporation into the performance measurement baseline. Near term effort should be 
planned and have budget in control accounts.  Far term effort that cannot be reasonably planned in the 
near term may be planned in summary level planning packages or maintained in Undistributed Budget 
(UB). Until contractual definitization, the near‐term work is continually planned. After definitization, any 
budget remaining in undistributed budget will be planned and budgeted within control accounts, summary 
level planning package packages, or management reserve, as soon as practical.  
1) Contractual change documents.
2) Change control logs (management reserve, 
undistributed budget, performance measurement 
baseline, and contract budget base).
3) Control account/work package/planning package 
plans.
4) Master schedules, intermediate schedules (if any), and 
detailed schedules.
5) Statement of work, WBS, and WBS dictionary.
29
Reconcile Current to 
Prior Budgets
The reconciliation of current budgets to prior budgets ensures the baseline 
maintains data integrity and reconciliation to the contract value.  
1) Budget changes are controlled and understood in terms of scope, resources, and schedule. Budgets 
reflect current authorized work. Budget revisions are made when work is added to the contract and are 
traceable from authorized contract target costs to the control account budgets or from management 
reserve. Management reserve may be used for authorized work that is in‐scope to the contract, but out of 
scope to a control account. Management reserve, therefore, may not be applied to completed work 
packages, except to compensate for the effect of routine accounting adjustments in accordance with the 
organization’s accounting practices.
2)Undistributed budget account should be distributed within a reasonable length of time subsequent to 
contract definitization or the program value finalization. It is recognized that some circumstances, such as 
delays in program direction, will affect the timely assignment of undistributed budget to control accounts.  
1) Contractual change documents.
2) Change control logs (management reserve, 
undistributed budget, performance measurement 
baseline, and contract budget base).
30
Control Retroactive 
Changes
Retroactive changes to the baseline may mask variance trends and prevent 
use of the performance data to project estimates of cost and schedule at 
completion.  
1) Control retroactive adjustments (including those in the current period), making only routine accounting 
adjustments, definitization of contract actions, rate changes, and economic price adjustments, customer‐
approved changes, or data entry corrections. Adjustments resulting from definitization of contract actions 
should be limited to affected work scope budgets. Changes that would arbitrarily eliminate existing cost 
and schedule variance should not be made. Rate changes and economic price adjustments are normal 
exceptions.
2) The cumulative values for the budgeted cost for work scheduled and budgeted cost for work performed 
are not adjusted for routine direct or indirect cost rate increases or decreases. This is necessary to ensure 
baseline integrity and accuracy of performance measurement data. Retroactive budget and/or 
performance adjustments may delay visibility of overall project variance from plan, thus reducing the 
alternatives available to managers for project redirection or termination.  
1) Change control logs.
2) Retroactive change control process including approval.
31
Prevent Unauthorized 
Revisions
Changes made outside the authorized baseline control processes 
compromise the integrity of performance trend data and delay visibility 
into overall project variance from plan, thus reducing the alternatives 
available to managers for project redirection or revisions. 
1) Prevent unauthorized revisions to the performance measurement baseline. Any changes to the project 
must be approved and implemented following the baseline management control process. This control 
precludes the inadvertent implementation of a budget baseline greater than the project budget. When the 
performance budget or schedule objectives exceed the project plan and are recognized in the performance 
measurement baseline, it is identified as an over‐target baseline (OTB).               
2) The decision to establish an over‐target baseline may result due to planning future work, planning in‐
process work, and/or adjusting cost or schedule variances. This permits an increase to the amount of 
budget for the remaining work. This creates a more realistic amount to adequately provide for reasonable 
budget objectives, work control, and performance measurement.  
1) Change control logs (management reserve, 
undistributed budget, performance measurement 
baseline, and contract budget base.
2) Control account/work package/planning package 
plans.
3)Master schedules, intermediate schedules (if any), and 
detailed schedules.
4) Statement of Work, WBS, and WBS dictionary.
6 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs
Earned Value Management Systems
REF :ANSI/EIA‐748 Intent Guide 
The 32 Guidelines Summary 
32
Document PMB 
Changes
By ensuring that budget and schedule revisions are documented and 
traceable, the integrity of the performance measurement baseline is 
maintained and can be verified. This provides control account managers 
with valid control account plans against which to execute and measure 
performance.  
The performance measurement baseline should always reflect the most current plan for accomplishing the 
effort. Authorized changes must be promptly recorded in the system and incorporated into all relevant 
planning. Planning and authorization documents must be updated accordingly, prior to the commencement 
of new work. 
1) Change control logs (management reserve, 
undistributed budget, performance measurement 
baseline, and contract budget base.
2) Control account/work package/planning package 
plans.
3) Work authorization documents.
4) Management performance reports or other 
management reports. 
7 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580

More Related Content

Earned Value Management - Intent 32 Guidelines Summary

  • 2. Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs 1 Define Work Scope  (WBS) The Work Breakdown Structure (WBS) is used as the basic building block for  the planning of all authorized work. The WBS is a product‐oriented division  of project tasks depicting the breakdown of work scope for work  authorization, tracking, and reporting purposes that facilitates traceability  and provides a control framework for integrated program management. It  should ensure that the Statement of Work (SOW) is entirely covered and  allow for the integration of technical, schedule, and cost information. The  WBS also facilitates communications as it establishes a common frame of  reference for customers, management, and Integrated Product Teams  (IPTs).  A WBS is a direct representation of the work scope in the project, documenting the hierarchy and  description of the tasks to be performed and their relationship to the product deliverables. The  WBS breaks down all authorized work scope into appropriate elements for planning, budgeting,  scheduling, cost accounting, work authorization, measuring progress, and management control.   The WBS must be extended to the level necessary for management action and control based on  the complexity of the work.  At a minimum, the WBS is extended to the level or levels at which  control accounts are established.  A WBS dictionary is typically used to define the work scope for  each unique element in the WBS.  1) Only one WBS is used per project and it contains all project  work, including revisions for authorized changes and  modifications. 2) The WBS contains all contract line items and end items. 3) The WBS identifies all WBS elements specified for external  reporting. 4) The WBS is extended at a minimum to the level(s) at which  control accounts are established. 5) The WBS elements should collectively provide a complete  definition of work scope requirements. 6) The WBS may evolve as the project requirements change. 2 Define Project  Organization (OBS) The OBS helps management focus on establishing the most efficient  organization by taking into consideration the availability and capability of  management and technical staff, including subcontractors, to achieve the  project objectives.   Assign organizational responsibility for the project work. An OBS is used to facilitate the  assignment of responsibility, accountability, and authority for all tasks to be performed. An OBS is  a direct representation of the hierarchy and provides a description of the organizations  established to provide resources as well as to plan and perform the work tasks. The OBS identifies  the organization responsible for each segment of work, including subcontracted and intra‐ organizational effort. The assignment of lower‐level work segments to responsible managers  should provide key control points for management purposes. When effort is subcontracted, the  applicable subcontractor is identified and related to the appropriate WBS element(s) and/or  organization charged with acquiring the subcontracted item.  1) All authorized work is assigned to organizational  elements. 2) Organization elements are work teams, functions, or  whatever organization units are used by the company for  execution of the program work efforts. 3) Major subcontractor work efforts are integrated into  the program structure.  3 Integrate Processes The integration of planning, scheduling, budgeting, work authorization, and  cost accumulation management processes provides the capability for  establishing the Performance Measurement Baseline (PMB), identifying  work progress, and collecting actual costs, facilitating management analysis  and corrective actions. The WBS and OBS allow summarization of cost data  from the detail level through both the WBS and the OBS to the appropriate  project level needed for management insight and control.   Integrate the technical, schedule, and cost elements of the project through project plans that  include schedules, budgets, authorization of work, and accumulation of costs, all consistent with  the budget plan. The work tasks are assigned to a WBS and OBS and are traceable to the planning  and budgeting system and the cost collection system. Establishment of a unique coding structure  facilitates the linkage between the planning, scheduling, budgeting, work authorization, cost  accumulation, and performance measurement processes.   1) Master, intermediate, and detail level schedules. 2) Manufacturing Requirements Planning (MRP) or  Enterprise Requirements Planning (ERP) operational  schedules. 3) Control account plans. 4) Management performance reports by WBS and OBS. 5) Responsibility Assignment Matrix (RAM). 6) Statement of Work. 7) Work authorizations. 4 Identify Overhead  Management Visibility into direct and indirect costs is essential for successful  management of a project. Therefore, it is important to have a documented  process and organizations established specifically to manage and control  indirect costs.   Indirect costs are for common activities that cannot be identified specifically with a particular  project or activity and should typically be budgeted and controlled separately at the functional or  organizational manager level. Clearly identify managers who are assigned responsibility and  authority for controlling indirect costs, and who have the authority to approve expenditure of  resources. The process for management and control of indirect costs, including assignment of  responsibility, is typically documented in the organization’s approved accounting procedures.  1) Cost Accounting Standards (CAS) disclosure statement. 2) Organizational chart. 3) Chart of accounts. Earned Value Management Systems REF :ANSI/EIA‐748 Intent Guide  The 32 Guidelines Summary  1 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
  • 3. Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs Earned Value Management Systems REF :ANSI/EIA‐748 Intent Guide  The 32 Guidelines Summary  5 Integrate WBS/OBS to  Create Control  Accounts The careful establishment of the control account structure ensures the  proper level of management is established based on the complexity of the  work and the capability of the organization.  It also establishes the lowest  level of performance measurement necessary for program management.  The integration of the WBS and OBS creates control accounts that facilitate schedule and cost  performance measurement. The control account is the point where the WBS tasks and OBS responsibility intersect. It is  defined as the point where a single functional organization or integrated product team has  responsibility for work defined to a single WBS element. There may be multiple control accounts  within a responsible OBS element when the effort within a WBS element must be segregated for  management control purposes driven by scope and exit criteria (i.e., completion of task scope).  The establishment of multiple control accounts should be determined by the control account’s  scope of the management tasks and consideration for planning and control of budgets, schedules,  work assignments, progress assessment, problem identification, and corrective actions.      1) Control accounts. 2) Responsibility Assignment Matrix (RAM). 3) Management performance reports. 6 Schedule with  Network Logic Scheduling authorized work facilitates effective planning, statusing, and  forecasting, all of which are critical to the success of all projects. The  integration of the technical, schedule, and cost aspects of the project  results in the: 1) Expected sequence of work. 2) Establishment of significant interdependencies between work packages  and planning packages (or lower‐level tasks/activities) that determine total  work time and critical path through the project.                3) Time‐phasing of authorized discrete work for use as a performance  measurement baseline. The scheduling process documents and the resulting project schedule provide a logical sequence  of work leading to a milestone, event, or decision point needed to ensure that the schedule  supports the project objectives. The master schedule aligns to the contractual period of  performance except when an Over‐Target Schedule (OTS) has been approved for implementation.   There is a clear definition of what constitutes commencement and completion of each work  package and planning package (or lower‐level task/activity). While no specific scheduling software  is required, there must be horizontal and vertical integration of the schedule through the  framework of the WBS and OBS. Government development programs or significant development efforts typically schedule the  discrete authorized work through the use of a network schedule. Production programs typically  schedule using a Manufacturing Requirements Planning (MRP) or Enterprise Requirements  Planning (ERP) tool employing a line of balance schedule that supports the project objectives.            1) Integrated network schedules including master,  intermediate (if any), and detailed schedules.                  2) MRP or ERP schedules, or planned order reports. 3) Control account plans (may be separate plans or detail  schedules). 4) Work authorization documents. 7  Set Measurement  Indicators Objective indicators enable measurement of work accomplished, thereby  allowing its accurate comparison to planned work. Meaningful performance  metrics enable better management insight and decision‐making, ensuring  that maximum time is allowed for management action to keep the project  on plan.  1) The purpose for identifying objective indicators is to provide a means to measure the quantity  of work accomplished – the earned value.  There is a direct relationship between the budget at  completion and earned value.  The time‐phased budget assigned to the work scope is the basis for  computing the earned value for work accomplished.  Performance measures are one aspect of an  integrated program management system as other processes control the quality and technical  content of the work performed. 2)Identify objective interim performance measures within control accounts (or lower‐level  tasks/activities) to enable accurate performance assessment each month. The master schedule  includes key program and contractual requirements. It enables the team to predict when  milestones, events, and program decision points can be expected to occur. Lower‐tier schedules,  when utilized, must contain specific control account (or lower‐level task/activity) start and finish  dates that are based on physical accomplishment and are clearly consistent with program time  constraints. 1) Integrated schedules including master, intermediate (if  any), and detailed schedules that identify contract  milestones and key events. 2) MRP or ERP production planned order reports. 3) Control account plans (may be separate plans or detail  schedules). 8 Establish Budgets for  Authorized Work The time‐phased performance measurement baseline that represents the  planned scope of all authorized work and schedule provides the program  manager a reference to assess project performance. It is controlled and  reconciled to the target cost plus authorized unpriced work less  management reserve. It represents the cumulative, time‐phased, budgeted  cost for work scheduled. The performance measurement baseline is a key  component of earned value management.  1) The Contract Budget Base (CBB) represents the value of all authorized work.  This includes the  negotiated contract cost (NCC) plus the estimated cost of any authorized unpriced work (AUW).  This CBB value forms the basis for program budgeting.           2) The assignment of budgets to scheduled segments of work produces a plan against which actual  performance can be compared. This is called the Performance Measurement Baseline (PMB). The  establishment, maintenance, and use of the PMB are indispensable to effective performance  measurement. The PMB should be in place as early as possible after project award or  Authorization to Proceed (ATP). 3) The PMB represents the time‐phased scope, schedule, and associated budget through the end  of the contract. It is the sum of the control accounts plus any summary level planning packages  (SLPP) and undistributed budget.  Undistributed budget is a transient account that is distributed to  control accounts, summary level planning packages, or management reserve as soon as practical  after definitization, or as contractually directed.    1) Control account plans. 2) Summary level planning packages. 3) Performance measurement baseline. 4) Undistributed budget logs. 5) Notification to the customer of an over‐target baseline  or over‐target schedule. 6) Work authorization document. 2 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
  • 4. Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs Earned Value Management Systems REF :ANSI/EIA‐748 Intent Guide  The 32 Guidelines Summary  9 Budget by Cost  Elements An essential part of project planning and establishing a performance  measurement baseline is the establishment of budgets for all the  authorized work. Identification of the budget cost elements documents the  required resources and places work scope with the performing  organization.  Through a work authorization process, establish budgets for all authorized work to be done by the  responsible organizational elements. No work should begin before the effort is authorized by an  initial work authorization. As budgets and schedules are established and approved for all the  authorized work at the control account level, the work authorization is updated as required. The  work authorization at the control account level is where the approved work scope, period of  performance, and budget are integrated. The control accounts identify the appropriate cost  elements (labor, subcontract, material, and other direct costs). It is important to include all  resources required to accomplish the work scope.  1) Control account plans by element of cost. 2) Work authorization documents. 3) Performance measurement baseline. 4) Undistributed budget logs. 5) Bills of Materials (BOM). 6) Responsibility assignment matrix . 7) Schedules, if resourced. 10 Create Work  Packages, Planning  Packages Budgets, established at the work package level identifying specific resource  requirements in dollars, hours, or other measurable units, provide the  detail for effective execution of the baseline plan. The resources are to be  time‐phased the way the detail work is to be accomplished. This approach  provides meaningful product‐related or management‐oriented events for  performance measurement. Where a control account cannot be planned in  work package detail, the work scope, budget, and schedule requirements  are held in planning packages. The master schedule may have more detail  below the work package/planning package level to support the  development of a realistic critical path, as applicable.  Effort contained within a control account is distributed into either work packages or planning  packages. Work packages are single tasks assigned to a performing organization for completion  and are natural subdivisions of control account effort, resulting in a definable end product or  event. Work package descriptions must clearly distinguish one work package effort from another.  When work packages are relatively short, little or no assessment of work‐in‐progress is required.  As work package length increases, work‐in‐progress measurement becomes more subjective,  unless objective techniques, such as discrete milestones with pre‐assigned budget values or  completion percentages, subdivide them. A key feature, from the standpoint of evaluating  accomplishment, is the desirability of having work packages that incorporate frequent, objective  indicators of progress.  1) Control account plans divided into work packages and  planning packages. 2) Control account schedules. 3) Control account time‐phased budgets.  11 Sum Detail Budgets to  Control Account The integrity of the performance measurement baseline requires that the  budget of the control account equal the sum of its work package and  planning package budgets. When the budget of the control account equals  the sum of its work package and planning package budgets, it prevents  duplicate recording of budgets.  All control accounts must contain a budget, schedule, and scope of work and should realistically  represent the work assigned and budgeted to the organizational units. In all cases, the value of  the budget assigned to individual work packages and planning packages within the control  account must sum to the total value authorized for the control account. A control account  manager should not have a budget without an assigned scope of work. Conversely a control  account manager should not have authorized scope without associated budget. 1) Control account plan total budget. 2) Work package budget. 3) Planning package budget. 12 LOE Planning and  Control Meaningful product‐ or management‐oriented events are critical for  performance measurement. Objective measurement of Level of Effort (LOE)  activity is impracticable and provides little, if any, visibility into actual  performance; therefore, its use must be minimized.  Each task on the project needs to be assessed to determine the best method to budget and  measure its progress toward completion. Level of effort is defined as having no measurable  output or product that can be discretely planned at the work package level. Level of effort must  be limited to those activities that are unable to be measured discretely to avoid distorting project  performance data. Level of effort work packages should be separately identified from discrete  effort work packages and apportioned effort work packages. Budgets for level of effort activity  must have a sound basis of estimate and be time‐phased to properly reflect when work will be  accomplished. LOE budgets may be planned at either the control account level or at the same  level as discrete or apportioned work packages.   1) Control account plans identify level of effort work  packages and budgets. 13 Establish Overhead  Budgets The overall value of establishing indirect budgets lies in the ability of  company management to manage cost elements that cannot be directly  assigned to individual cost objects (products).  By comparing actual indirect  expenses to established indirect budgets, the company can determine if the  absorption of indirect expenses based on existing documented allocation  schemes is on track or if allocation rates will need to be adjusted.  The  accurate assignment of indirect expenses, therefore, ensures that each  program will only receive its fair share of indirect costs.  Establish indirect budgets at the appropriate organizational level for each pool and cost sub‐ element. It is important to have an indirect budgeting and forecasting process, because indirect  costs can account for a major portion of the cost of any project. As such, the budgetary control  and management of this category of cost cannot be overlooked or minimized. Indirect budgets on  the project are established and planned with the established direct budgets consistent with the  method by which allocation of indirect costs will ultimately be made to the project. This  methodology is normally described in the organization’s accounting procedures.  1) Documented process for managing indirect costs. 2) Organizational structure identifying ownership  responsibility and authority levels. 3) Indirect cost policies and procedures. 4) Chart of accounts. 14 Identify Management  Reserve and  Undistributed Budget To ensure that budget for newly authorized efforts remains tied to the  associated scope during the initial planning process, Undistributed Budget  (UB) has been designated as the short‐term holding account. Once the  responsible organization(s) has been identified, the budget will transfer  from undistributed budget to the appropriate control account(s). This  ensures budget and scope will not be transferred independently.  1) Identify and control management reserve and undistributed budget. Management reserve is  budget set aside for unplanned events that may arise during the course of the project. Because  management reserve is budget that is not yet tied to work, it does not form part of the  performance measurement baseline. The management reserve budget should be commensurate  with the level of risks and opportunities identified by the project or withheld for management  control purposes. 2) Undistributed budget is budget that is applicable to specific project effort, but has not yet been  distributed below the project level either directly to control accounts or to summary level  planning packages. It is a transient amount because, once it is distributed to either control  accounts or to summary level planning packages, it ceases to be undistributed budget. Because  undistributed budget is budget that is tied to work, it does form part of the performance  measurement baseline. Undistributed budget accounts are to be cleared in a reasonably timely  manner as work scope is finalized and distributed to control accounts or to summary level  1) Project control logs (management reserve,  undistributed budget, performance measurement  baseline, and contract budget base). 2) Management performance reports. 3 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
  • 5. Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs Earned Value Management Systems REF :ANSI/EIA‐748 Intent Guide  The 32 Guidelines Summary  15 Reconcile to Target  Cost Goal A project baseline that reflects the common agreement between the two  parties provides a common reference point for progress assessment. It  provides recognition of contractual requirements and precludes  unauthorized changes to the performance measurement baseline. The  project target cost must be reconciled with the performance measurement  baseline and management reserve.   Reconcile the project value (target cost plus authorized, unpriced work) with the sum of all control  account budgets, indirect budgets, management reserves, and undistributed budgets.  1) Project control logs (management reserve,  undistributed budget, performance measurement  baseline, and contract budget base) reconciled to project  target cost. 2) Management performance reports. 3) Internal report showing the summarization from cost  account to the performance measurement baseline. 16 Record Direct Costs Direct cost must be assigned to a project consistent with the pertinent  budgets in order to achieve effective performance management. A project’s  cost‐charging structure established in the accounting system should help  ensure that actual costs collected are directly compared with associated  budgets for that work.   1) Accumulate direct costs in the formal accounting system in a manner consistent with the way  the related work is planned and budgeted. Actual costs reported in the performance reports agree  with the costs recorded in the general books of account (accounting system) or can be explained  as timing differences.  At a minimum, actual costs are collected at the control account level to  enable summarization of cost by both the WBS and OBS.  Timing differences that may occur  between the accounting system and project performance reports must be reconcilable. 2) Subcontracts also require special consideration. Subcontract costs must be accrued in a timely  manner consistent with the schedule status. This may require the use of estimated costs or the  equivalent import from the subcontractor’s books of record or report.   1) Reconciliation of project costs with the accounting  system. 2) Actual costs are reported at the control account level  at a minimum. 3) Reconciliation of subcontract reported actual costs to  subcontract payments. 4) Internal and external performance reports for  subcontractors. 17 Summarize Direct  Costs by WBS  Elements Actual costs need to be available at all levels of the WBS to support project  management with performance measurement data. Cost collection  accounts mapped to the WBS. The WBS roll‐up structure contains no  division/allocation of lower‐level cost to multiple higher‐level WBS  elements, which helps to ensure performance measurement data integrity  when summarized by WBS.   A work order/job order/task code charge number structure must exist that uniquely identifies  costs at the control account level allowing for accumulation and summarization of costs to higher  levels of the work breakdown structure. Through the use of this coding structure, allowable costs  collected within the control account by element of expense roll‐up from the control account level  through the WBS to the top level without being divided among two or more higher‐level WBS  elements. Cost collection accounts map to the WBS, and the WBS roll‐up structure contains no  division/allocation of lower‐level cost to multiple higher‐level WBS elements. When common  costs are collected in separate control accounts for like items or services they are allocated to  appropriate control accounts in each project.   1) Cost collection account structure. 2) WBS/cost collection mapping. 3) Management performance reports. 18 Summarize Direct  Costs by OBS Elements Actual costs need to be available at all levels of the OBS to support project  management with performance measurement data. Cost collection  accounts mapped to the OBS, and the OBS roll‐up structure containing no  division/allocation of lower‐level cost to multiple higher‐level OBS  elements, helps to ensure performance measurement data integrity when  it is summarized by OBS.   Allowable costs collected within the control account by element of expense “roll‐up”, from the  control account level through the OBS, to the top level without being divided at any level among  two or more higher‐level elements. This guideline and the one before it are identical, with the  exception that this one deals with OBS data summarization while the previous one dealt with WBS  data summarization. In either case the intent is the same: actual cost collected at the control  account level may not be rolled up (i.e., summarized) to multiple higher‐level elements. When  common costs are collected in separate control accounts for like items or services, they are  allocated to appropriate control accounts in each project.   1) Responsibility assignment matrix. 2) Organization charts. 3) OBS structure (roll‐up scheme). 4) Management performance reports. 19 Record/Allocate  Indirect Costs Visibility into direct and indirect costs is essential for successful  management of a project. Therefore, it is important to have a documented  process and organizations established specifically to manage and control  indirect costs.  Indirect costs are for common activities that cannot be identified specifically with a particular  project or activity and should typically be budgeted and controlled separately at the functional or  organization managerial level. Record all indirect costs for the project in the accounting system.  Allocate them to the recorded direct costs per the documented procedure to ensure that all  projects benefiting from the indirect costs will receive their fair share.  1) Cost collection account structure. 2) WBS/cost collection mapping. 3) Cost accounting standards disclosure statement. 20 Identify Unit and Lot  Costs A manufacturing accounting system capable of isolating unit and lot costs in  a production environment should allow the flexibility to plan, measure  performance, and forecast in a more efficient way when there are multiple  projects in the same production line.   When using equivalent units, or lot costs budgeting, ensure that the accounting system produces  actual unit, equivalent unit, or lot costs for purposes of measuring cost performance.  Typically  this is accomplished through the use of a charge number structure, the manufacturing planning  systems, or equivalent capability. On production contracts or projects where multiple similar units  are being delivered, or when units are taken off the line in more or less a random order according  to the delivery agreements of the different customer’s projects, it is sufficient to establish  “equivalent unit cost” (i.e., all things being equal, each unit’s cost is approximately equivalent to  every other unit’s cost).  1) Project cost collection structure (MRP). 2) ERP system supports the identification of unit costs,  equivalent unit costs, or lot costs when needed, including  differentiation of work in process. 4 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
  • 6. Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs Earned Value Management Systems REF :ANSI/EIA‐748 Intent Guide  The 32 Guidelines Summary  21 Track and Report  Material Costs and  Quantities 1) The establishment of a valid comparison of planned material costs for  completed work with the actual material costs for that work provides the  basis for realistic evaluation of cost deviations and ultimately facilitates  cost at complete projections.  Residual inventory provides visibility into  excess material for the current deliverables available for replacement of  failures in the current project or future projects having similar deliverables.   2) Long lead critical material items may require special considerations for  planning and measuring progress.  Contracting methods should be  considered that support objectives and promote the use of progress  methods to meet the needs of integrated program management.  Material costs must be accurately charged to contract control accounts using recognized,  acceptable costing techniques. The need for accurate comparison of material costs to material  budgets and earned value requires that the appropriate point of performance measurement for  material is established. The generally acceptable points for measuring material progress are:             1) Point of receipt (acceptance). 2) Point of stock (inventory). 3) Point of issue to work in process (consumption). 1) Management performance reports. 2) Control account plans. 3) Material system reports. 22 Calculate Schedule  Variance and Cost  Variance Earned Value Management System (EVMS) performance data reconciles to  the general books of account (accounting system) and provides for  management control. Visibility into project performance helps the project  manager to focus resources on those areas in need of attention. On at least a monthly basis, generate schedule variance and cost variance data that supports  management control needs by allowing the project manager to focus on those areas in need of  attention. The intent of this guideline is to recognize that analysis must be accomplished on a  regular, periodic basis. It is critical that the calculation of earned value (see guidelines 7 and 10) be  based consistently with the manner used to establish the budgets (see guidelines 8, 10, and 12).  This ensures a generation of valid variances for analysis purposes.  All data analyzed must come  from, or be reconcilable with, the earned value management system (BCWS, BCWP, and ACWP)  and the accounting system.  1) Monthly performance reports (cost variance, schedule  variance, and variance at completion analysis).                 2) Variance analysis data (root causes, impacts at  completion, and management actions). 23 Identify Significant  Variances for Analysis The ability to analyze deviations from the established plan permits  management at all levels to rapidly and effectively implement corrective  actions in an effort to regain project/contract objectives.  Without this  visibility into and the understanding of plan deviations, the success of the  project can be jeopardized.  Additionally, insight into future cost and  schedule performance, based on the analysis of variances, will be  facilitated.   1) The purpose of this guideline is to ensure both significant schedule and cost variances are  analyzed, at least monthly, at a level of detail required to manage the effort; i.e., to enable  management decision‐making and corrective action.               2) Comparing the budget value of work completed to the budget value of work scheduled during a  given period of time provides a valuable indication of schedule status in terms of dollars‐worth of  work accomplished. This schedule variance (SV) may not clearly indicate whether or not scheduled  milestones are being met, since some work may have been performed out of sequence or ahead  of schedule while other work has been delayed. Schedule variance does not indicate whether a  completed activity is a critical event or if (or by how much) delays in an activity’s completion will  affect the completion date of the project.   1) Variance analyses (budget based schedule variances  and cost variances). 2) Management action plans. 3) Updated schedule task completion and cost‐at‐ completion forecasts. 24 Analyze Indirect Cost  Variances Ongoing indirect cost analysis provides visibility into potential indirect cost  overruns and the opportunity to develop and implement management  action plans to meet project objectives. Indirect rate forecast and control are crucial to meeting project cost objectives. This guideline  requires a monthly indirect cost analysis, by those assigned responsibility, comparing indirect  budgets to indirect actual costs and explaining the cause of resultant variance(s). The importance  of analyzing indirect cost performance requires the exercise of maximum discipline in following  the established indirect cost control procedures. The results of indirect analysis are provided to  program and business managers for their use in forecasting the impact to the program Estimate at  Completion (EAC).  1) Indirect cost variance analyses. 2) Indirect cost management action plans. 3) Indirect cost updated schedule and cost forecasts. 25 Summarize  Information for  Management Understanding the relationship among scope, cost, schedule, and risk is  critical to successful project execution. Variances provide an understanding  of project conditions, allowing the project manager to properly address  project issues, risks, and opportunities. They also identify significant  problem areas coming from all levels of the organization and project scope  of work, derived from the same data sources. Variances provide valuable  management information.  Use the same data for internal management needs and for reporting to the customer. Since the WBS and  the OBS exist as a formal and disciplined framework for project management and also provide a formal  structure for the comprehensive roll‐up of all data elements, they become the ideal framework for  summarizing data from the control account level to the management reporting level. Summarizing  performance information assists senior levels of management to focus on the significant problems that  require their intervention.   1) Variance analyses. 2) Schedule and cost performance reports. 3) Management action plans. 4) Updated schedule and cost forecasts. 26 Implement Corrective  Actions Earned value management information provides management with early  insight into the extent of problems. Management action is required to  mitigate the impacts on the project objectives. 1) Identify and implement corrective actions based on earned value variance analysis to achieve project  objectives. Regular monitoring of the performance data helps keep the program within its cost and  schedule baseline objectives. 2) Performance measurement data should be utilized by all levels of management to promote effective  project execution. Because of this, the data produced by the earned value management system must be  available to managers on a timely basis and must be of sufficient quality to ensure that effective integrated  program management decisions can be made as a result of its analysis. The project’s internal reports and  the reports forwarded to their customer must indicate the overall cost and schedule impacts of such  problems on the project.   1) To‐Complete Performance Index (TCPI). 2) Independent completion estimates. 3) Risk and opportunity management data and similar  metrics. 4) Management action plans and review briefings. 5 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
  • 7. Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs Earned Value Management Systems REF :ANSI/EIA‐748 Intent Guide  The 32 Guidelines Summary  27 Revise Estimate at  Completion (EAC) A properly established and maintained estimate at completion (EAC) will  ensure continuing visibility into the cost, schedule, risks and opportunities,  as well as the resource needs (e.g., labor, material, etc.) for the remaining  work that is essential to project success for both the customer and the  contractor.  Accurate estimates support the customer’s ability to provide  sufficient funding to the project and enhance internal management’s  visibility into critical issues and resource requirements.   1) The control account level is where the approved work scope, period of performance, budget, and  estimate at completion (EAC) are integrated.  The estimates at completion are summarized up through the  WBS and OBS to the program level for management visibility and control.  The control account managers  are responsible for maintaining the control account level latest revised estimate to complete that is  assessed on a monthly basis. Periodically, a comprehensive or bottom‐up estimate at completion should be  prepared using all available information to arrive at the best possible estimate at completion. 2) For the monthly estimates to complete (ETC), the control account manager should review the status of  the expended effort and the achievability of the forecast and significant changes briefed to program  management. This analysis should focus on performance to date within the control account, an assessment  of the effort to complete the remaining work, and an evaluation of the type and quantity of resources  required to complete the effort. Issues, risks and opportunities should also be considered in this analysis.  When updates are made to existing forecasts of the schedule and cost to complete, significant changes are  briefed to program management. Prudent maintenance of the control account‐level estimates at  completion ensures that the EAC reflects a valid projection of project costs.   1) Control account plans. 2) Documented process for developing EACs, including  subcontractor EAC integration. 3) Basis of estimates. 4) Risk and opportunity management plans  (identification, analysis, and handling plans).                 5) Updated schedule task completion and cost‐at‐ completion forecasts. 28 Incorporate Changes  in a Timely Manner A properly maintained performance measurement baseline is crucial to  effective program management.  The timely and accurate incorporation of  contractual changes ensures that the information generated from the  execution of the baseline plan provides an accurate picture of progress and  facilitates correct management actions and decisions.   1) Incorporate the work scope for authorized changes into the performance measurement baseline in a  documented, disciplined, and timely manner. The timely and accurate incorporation of authorized and  negotiated changes into the performance measurement baseline ensures that valid performance  measurement information is generated for the new scope being executed. Adherence to this guideline  helps to ensure that budget, schedule, and work remain coupled.                  2) For unpriced change orders, the contractor will develop its best estimate for planning and budgeting  purposes for incorporation into the performance measurement baseline. Near term effort should be  planned and have budget in control accounts.  Far term effort that cannot be reasonably planned in the  near term may be planned in summary level planning packages or maintained in Undistributed Budget  (UB). Until contractual definitization, the near‐term work is continually planned. After definitization, any  budget remaining in undistributed budget will be planned and budgeted within control accounts, summary  level planning package packages, or management reserve, as soon as practical.   1) Contractual change documents. 2) Change control logs (management reserve,  undistributed budget, performance measurement  baseline, and contract budget base). 3) Control account/work package/planning package  plans. 4) Master schedules, intermediate schedules (if any), and  detailed schedules. 5) Statement of work, WBS, and WBS dictionary. 29 Reconcile Current to  Prior Budgets The reconciliation of current budgets to prior budgets ensures the baseline  maintains data integrity and reconciliation to the contract value.   1) Budget changes are controlled and understood in terms of scope, resources, and schedule. Budgets  reflect current authorized work. Budget revisions are made when work is added to the contract and are  traceable from authorized contract target costs to the control account budgets or from management  reserve. Management reserve may be used for authorized work that is in‐scope to the contract, but out of  scope to a control account. Management reserve, therefore, may not be applied to completed work  packages, except to compensate for the effect of routine accounting adjustments in accordance with the  organization’s accounting practices. 2)Undistributed budget account should be distributed within a reasonable length of time subsequent to  contract definitization or the program value finalization. It is recognized that some circumstances, such as  delays in program direction, will affect the timely assignment of undistributed budget to control accounts.   1) Contractual change documents. 2) Change control logs (management reserve,  undistributed budget, performance measurement  baseline, and contract budget base). 30 Control Retroactive  Changes Retroactive changes to the baseline may mask variance trends and prevent  use of the performance data to project estimates of cost and schedule at  completion.   1) Control retroactive adjustments (including those in the current period), making only routine accounting  adjustments, definitization of contract actions, rate changes, and economic price adjustments, customer‐ approved changes, or data entry corrections. Adjustments resulting from definitization of contract actions  should be limited to affected work scope budgets. Changes that would arbitrarily eliminate existing cost  and schedule variance should not be made. Rate changes and economic price adjustments are normal  exceptions. 2) The cumulative values for the budgeted cost for work scheduled and budgeted cost for work performed  are not adjusted for routine direct or indirect cost rate increases or decreases. This is necessary to ensure  baseline integrity and accuracy of performance measurement data. Retroactive budget and/or  performance adjustments may delay visibility of overall project variance from plan, thus reducing the  alternatives available to managers for project redirection or termination.   1) Change control logs. 2) Retroactive change control process including approval. 31 Prevent Unauthorized  Revisions Changes made outside the authorized baseline control processes  compromise the integrity of performance trend data and delay visibility  into overall project variance from plan, thus reducing the alternatives  available to managers for project redirection or revisions.  1) Prevent unauthorized revisions to the performance measurement baseline. Any changes to the project  must be approved and implemented following the baseline management control process. This control  precludes the inadvertent implementation of a budget baseline greater than the project budget. When the  performance budget or schedule objectives exceed the project plan and are recognized in the performance  measurement baseline, it is identified as an over‐target baseline (OTB).                2) The decision to establish an over‐target baseline may result due to planning future work, planning in‐ process work, and/or adjusting cost or schedule variances. This permits an increase to the amount of  budget for the remaining work. This creates a more realistic amount to adequately provide for reasonable  budget objectives, work control, and performance measurement.   1) Change control logs (management reserve,  undistributed budget, performance measurement  baseline, and contract budget base. 2) Control account/work package/planning package  plans. 3)Master schedules, intermediate schedules (if any), and  detailed schedules. 4) Statement of Work, WBS, and WBS dictionary. 6 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580
  • 8. Sr Guideline Description Management Value Intent Objective Evidence May Be Found In These Typical Outputs Earned Value Management Systems REF :ANSI/EIA‐748 Intent Guide  The 32 Guidelines Summary  32 Document PMB  Changes By ensuring that budget and schedule revisions are documented and  traceable, the integrity of the performance measurement baseline is  maintained and can be verified. This provides control account managers  with valid control account plans against which to execute and measure  performance.   The performance measurement baseline should always reflect the most current plan for accomplishing the  effort. Authorized changes must be promptly recorded in the system and incorporated into all relevant  planning. Planning and authorization documents must be updated accordingly, prior to the commencement  of new work.  1) Change control logs (management reserve,  undistributed budget, performance measurement  baseline, and contract budget base. 2) Control account/work package/planning package  plans. 3) Work authorization documents. 4) Management performance reports or other  management reports.  7 Summarized By : https://linkedin.com/in/muhammad-el-chammakh-pmp-rmp-6853a580