-1

I entered into a contract to have my sewer line replaced, and in the acceptance of this contract, I stated that my homeowner's insurance was covering the cost. I told them in the acceptance email that I had paperwork for the claim for them to fill out.

A month later, they showed up and repaired but never sent in the insurance papers. After the job was done, they finally filled them out, but my insurance denied the claim. If this was filled out and turned in within the month that they had the paperwork, this project would have been cancelled, and I would not be paying four times the amount that other contractors charge. I feel this is a breach of contract. Do I have a leg to stand on?

2 Answers 2

2

"I entered ..." is not "My insurance company entered ..."

It appears that the contract terms were that they would do the work, you would pay them and they would fill out some paperwork to help you lodge an insurance claim. It seems that they did everything the contract required of them.

Unless you made your acceptance conditional on them filling out the forms first?

2

I entered into a contract to have my sewer line replaced, and in the acceptance of this contract, I stated that my homeowner's insurance was covering the cost. I told them in the acceptance email that I had paperwork for the claim for them to fill out.

That isn't how acceptance works. Acceptance means that you accept the terms that were offered to you without modification. If you incorporate additional terms (e.g. requiring them to complete insurance paperwork) then that is a counter-offer. A counter-offer has the effect of extinguishing the original offer (making it no longer capable of acceptance), and it is then up to the other party to accept your new offer. With that said, acceptance can be by conduct. If the contractor turned up to the job after receiving your counter-offer, that could be considered acceptance.

I don't know how you worded your email. In the alternative, it could be that you gave a clear and unconditional acceptance of their original terms and with a separate follow-up request to complete paperwork which wasn't linked to the acceptance. In that scenario the request isn't part of the contract.

I feel this is a breach of contract. Do I have a leg to stand on?

This depends on the exact wording of your email. If your email constitutes a counter-offer which states that they needed to submit documentation to the insurer within 1 month then there could be a breach of contract. If you made a counter-offer which didn't specify a time limit then the situation is more difficult. You may be able to apply Section 52 of the Consumer Rights Act 2015:

(1) This section applies to a contract to supply a service, if—

(a) the contract does not expressly fix the time for the service to be performed, and does not say how it is to be fixed, and

(b) information that is to be treated under section 50 as included in the contract does not fix the time either.

(2) In that case the contract is to be treated as including a term that the trader must perform the service within a reasonable time.

(3) What is a reasonable time is a question of fact.

The fact that you appeared to allow them to carry out the repairs after 1 month despite not having submitted the insurance paperwork might suggest that the delay was treated by the parties as being reasonable. It might also be reasonable for the contractor to wait until the works were underway or complete in order to have the necessary information to be able to complete the paperwork accurately. As noted in sub-section (3) above, it will be for the Court to decide what is or is not reasonable based on the circumstances of your case.

You must log in to answer this question.

Not the answer you're looking for? Browse other questions tagged .