I'm using Project 2010 with a project base calendar that has been loaded with exceptions for company holidays. However, when I add tasks to it and resource load them, it is ignoring the base calendar and spreading hours against a holiday exception as a working day in the Gantt.
This problem is fixed if I assign the project base calendar to either the task or the resource but by default shouldn't Project use the base calendar for all tasks and resources when a specific calendar is NOT assigned to that task or resource?